Skip to main content

Installing and configuring EC-M/L/XL locations

The following pages describe how EC-M/L/XL sites can be installed and configured after ordering.

Installation steps

Commissioning occurs in the following steps:

  1. Installation of the router(s)
  2. Activation of the router(s) (ZTP process)
  3. For EC-XL: Interconnection of the router for greater service availability
  4. Installation of the hardware for Mobile Backup or Application Based Routing (optional)
  5. Configuration of the site
note

You can also carry out the configuration (step 5) of the site before steps 1 to 4 in the Enterprise Connect Dashboard. The sites are already visible in the EC Dashboard a few minutes after ordering. The configuration is then automatically adopted after commissioning (steps 1 to 4) has occurred.

Router overview

To get an overview of the available ports and status LEDs of the individual router types, please refer to the following pages: