Installing and configuring EC-M/L/XL locations
The following pages describe how EC-M/L/XL sites can be installed and configured after ordering.
Installation steps
Commissioning occurs in the following steps:
- Installation of the router(s)
- Activation of the router(s) (ZTP process)
- For EC-XL: Interconnection of the router for greater service availability
- Installation of the hardware for Mobile Backup or Application Based Routing (optional)
- Configuration of the site
note
You can also carry out the configuration (step 5) of the site before steps 1 to 4 in the Enterprise Connect Dashboard. The sites are already visible in the EC Dashboard a few minutes after ordering. The configuration is then automatically adopted after commissioning (steps 1 to 4) has occurred.
Router overview
To get an overview of the available ports and status LEDs of the individual router types, please refer to the following pages: